Lessons from the Streetcar
Published on: May 08, 2015
Published in:
Trenchless World, May 2015
Authors:
Bradford Miller, P.G. and Dennis Doherty, P.E., Haley & Aldrich; and Mark Smith, P.E., Southern Company/Georgia Power
Synopsis:
The 2.7-mile (4.3km) Atlanta Streetcar project, completed in 2015, reconnected downtown Centennial Park with several historic sites isolated from the city center by interstate highways.
The project included relocation of a 115kV electric circuit below historic Auburn Avenue, using a 1,860ft-long (567m) HDD completed on behalf of Georgia Power. The high-pressure fluid-filled (HPFF) cable duct replaced a direct-buried power line installed in 1959 that was located directly beneath the new streetcar trackbed.
Strategic planning and co-operative relationships between the owner, contractor and design engineer ensured the success of the project, despite its challenging urban location. This article conveys successful lessons for other engineers/owners considering an urban HDD installation.
Click here to download this article.
atlanta-streetcar-hdd-trenchless-world (313 KB)